Kilby House Build Progress – Phase 1 near completion

Written by admin on . Posted in Tenant News

With critical system testing complete, Keysource are now putting the final touches to the first phase of AIMES 34, 000 sq ft MAin-Corridor1-323x272Kilby House Data Centre development ready for handover. With up to 1MW IT load capacity emplaced Keysource’s innovative and highly efficient design will deliver class leading energy efficiency from day one. AIMES a staff have been
 working with Keysource over the last week testing power and cooling and ensuring that the advanced monitoring and communication systems are integrated into AIMES existing Data Centre systems. Some of AIMES existing clients have already visited the new facility and were impressed by the high standards of resilience, efficiency and cleanliness – and it is still a construction site! Phase 1 of the new development will be fully operational and open for business from 1st September and both AIMES and Keysource are looking forward to starting on Phase 2.